NPD report reveals causes of cost overruns for field developments on the Norwegian shelf

14/10/2013 The Norwegian Petroleum Directorate (NPD), on assignment from the Ministry of Petroleum and Energy (MPE) has reviewed five field developments on the Norwegian shelf to uncover why some developments finish in line with their estimated cost target, while others are much more expensive than planned.

The report deals with field developments in excess of NOK 10 billion, with plans for development and operation approved during the period 2006 – 2008. The specific fields involved are Skarv, *Yme, Valhall redevelopment, Tyrihans and Gjøa.

Most projects on the Norwegian shelf end up with development costs within the range of uncertainty stated in the plan for development and operation (PDO) (+/- 20%), but there are some projects with very extensive overruns.

The NPD’s report reviews both projects with major overruns, and projects that have been carried out on schedule and with costs within the range of uncertainty.

The report also shows that overruns are not a Norwegian phenomenon. Several studies reveal the same trend internationally.

The NPD’s work uncovered four main factors in project implementation that are important for the project’s success:

  • Meticulous work in the engineering phase, that is, in the early phase. This will form the basis for decisions and the ongoing work in the project
  • A clear contract strategy which takes the project’s most important risk elements into account, such as use of new technology and major equipment components
  • Thorough prequalification of the suppliers who contribute to the project
  • Good operator follow-up of the project. This is crucial, regardless of where in the world the construction takes place

All of the projects reviewed by the NPD were built during a period when the market was tight. The high level of activity is a contributing factor to the cost overruns, however, the most important causes lie in the planning, contract strategy, supplier follow-up and project follow-up.

Yme, Valhall redevelopment and Skarv have the largest cost overruns. Gjøa and Tyrihans were completed on time and within the estimated cost range presented in the PDO.

The objective of this work has been to extract lessons learned from the findings, both for the industry and for the authorities.

“We believe that the experience gained from these projects can be transferred to other projects. It is therefore important that the industry studies the findings in our report,” says director Arne Holhjem in the NPD.

“It is important to clarify the responsibilities in a field development. The licensees are responsible for implementing the project within the framework outlined in the PDO. This is a basic principal for our follow-up of the projects.”

“Now we in the NPD have to work through these findings to see how this will impact our follow-up efforts in connection with field developments,” says Arne Holhjem.

*The Yme project was included even though the original investment estimate was less than NOK 10 billion, because the final investments ended up being higher than NOK 10 billion. Tyrihans is included because the development was approved by the Storting (Parliament) in late 2005.


Contact in the Norwegian Petroleum Directorate
Eldbjørg Vaage Melberg, tel.+ 47 51 87 61 00

 

Updated: 05/11/2013

Latest news

Production figures December 2021
20/01/2022 Preliminary production figures for December 2021 show an average daily production of 2 108 000 barrels of oil, NGL and condensate
APA 2021: 28 companies offered ownership interests
18/01/2022 18 January 2022, 28 companies have received offers of ownership interests in a total of 53 production licences on the Norwegian Shelf in the Awards in Predefined Areas (APA) 2021.
Dry well east of the Ormen Lange field in the Norwegian Sea – 6306/9-1
17/01/2022 Lundin Energy Norway AS, operator of production licence 886, is in the process of concluding the drilling of wildcat well 6306/9-1.
Record-high revenues from the Norwegian shelf
13/01/2022 The combination of high production of oil and gas from a total of 94 fields, significant demand and high commodity prices led to a historically high level on the State's export revenues from petroleum. Much of this is due to record-high gas prices.
Follow the livestream of The Shelf 2021
12/01/2022 Thursday, 13 January 2022 from 10:00 Director General Ingrid Sølvberg gives a summary of the Shelf in 2021.
Oil discovery near the Fram field in the North Sea – 35/10-7 S and 35/10-7 A
07/01/2022 Equinor Energy AS, operator of production licence 630, has concluded the drilling of wildcat well 35/10-7 S and appraisal well 35/10-7 A.
Drilling permit for wells 25/2-23 S, 25/2-23 A and 25/2-23 B
28/12/2021 The Norwegian Petroleum Directorate (NPD) has granted Aker BP ASA a drilling permit for wells 25/2-23 S, 25/2-23 A and 25/2-23 B, cf. Section 13 of the Resource Management Regulations.
Smarter use of data can increase value creation
21/12/2021 The Norwegian Petroleum Directorate (NPD) has taken an initiative to discuss with the industry which steps can be taken to increase value creation through better use of data.
Production figures November 2021
21/12/2021 Preliminary production figures for November 2021 show an average daily production of 1 999 000 barrels of oil, NGL and condensate.
Five companies want to store CO2
16/12/2021 The Ministry of Petroleum and Energy has received applications from five companies in connection with the announcement of two areas associated with injection and storage of CO2 on the Norwegian continental shelf.