11/01/2013 A considerable number of plans for development and operation (PDOs) have been submitted in 2012: six in the North Sea and two in the Norwegian Sea. Of these, the authorities approved four in the North Sea and two in the Norwegian Sea before the end of the year.

The North Sea

One of the approved developments is the Total-operated 30/7-6 «Martin Linge» (formerly «Hild»), which was proven as early as 1978. The reservoirs contain gas with high pressure and high temperature, and oil has also been proven. The plan is to develop the field with a permanent production facility.

16/1-8 «Edvard Grieg» (formerly «Luno») has also been approved for development with a permanent facility. This will be the first major development project for Lundin in Norway. The facility will also handle final processing of the production from Ivar Aasen.   

Three plans involving subsea development have also been approved: Marathon-operated «Bøyla» which will be tied to Alvheim, Statoil-operated «Svalin» which will be tied to Grane, and «Jette» which will be tied to Jotun. «Jette» is the first development project for Det norske oljeselskap, and the development plan was submitted in 2011.

The two PDOs that have not yet been approved are for the Statoil-operated 15/5-1 «Dagny» and the Det norske-operated 16/1-9 «Ivar Aasen» (formerly «Draupne»), which will be unitised with «Edvard Grieg». Both will be developed with fixed production facilities, according to the plans.


The Norwegian Sea

The plan for Statoil-operated «Skuld» was approved in January 2012. The field will produce oil from three subsea templates tied to the Norne vessel.

The plan for seabed compression on the Statoil-operated Åsgard field was approved in March 2012. Compressors will be installed on the seabed to increase production from the Mikkel and Midgard fields. Åsgard gas compression represents new technology that can contribute to improve gas recovery and extend the lifetime of other fields.

A PDO was recently also submitted for the 6707/10-1 gas and condensate discovery «Aasta Hansteen» (previously known as «Luva»), about 140 kilometres north of the Norne field. The plan is to transport the gas to Nyhamna in Møre and Romsdal in a gas pipeline, which will be constructed with sufficient capacity to also accommodate gas from other developments in the area.

The Plan for Installation and Operation (PIO) of this pipeline, called Polarled, was also submitted in January this year.


More developments ahead

The oil companies intend to submit about 20 plans for development and operation over the next two years. Of these, about ten may come in the North Sea, six in the Norwegian Sea and two in the Barents Sea, where no PDOs have been approved since Goliat in 2009.

 

Updated: 11/01/2013

Latest news

Production figures March 2024
19/04/2024 Preliminary production figures for March 2024 show an average daily production of 2 086 000 barrels of oil, NGL and condensate.
Norwegian Offshore Directorate publishes new deep sea data
17/04/2024 In June 2022, the Norwegian Offshore Directorate published data collected up to 2022. The Directorate is now releasing deep sea data gathered from 2022 to 2024.
The future in the Barents Sea is here now
17/04/2024 The Johan Castberg ship will soon be heading north. With the ship in place, the plan is to have three producing fields in the Barents Sea by the end of the year.
Oil discovery in the North Sea
17/04/2024 Vår Energi has made an oil discovery in "Ringhorne Nord" (wells 25/8-23 S and 25/8-23 A & B), north of the Ringhorne Øst field, 200 kilometres northwest of Stavanger.
Entering into cooperation with Greenland and Denmark on seabed minerals
15/04/2024 This cooperation involves an MoU – Memorandum of Understanding – with the aim of acquiring additional knowledge on seabed minerals.
Drilling permit for well 35/11-27 S
03/04/2024 The Norwegian Offshore Directorate has granted Wintershall Dea Norge AS drilling permit for well 35/11-27 S in production licence 248, cf. Section 13 of the Resource Management Regulations.
Seabed minerals – step by step
26/03/2024 Seabed minerals represent a new and exciting opportunity for Norway, and a chance for us to be a pioneer nation – much like we have been within the oil and gas industry, both as regards stewardship of resources and development of technology.
Drilling permit for well 24/6-5
25/03/2024 The Norwegian Offshore Directorate has granted Aker BP ASA drilling permit for well 24/6-5 in production licence 203, cf. Section 13 of the Resource Management Regulations.
Sign up for Technology Day 2024
22/03/2024 Now, a very exciting program with lectures from a variety of companies is ready for Technology Day on June 6th.
The industry gives the Norwegian Offshore Directorate high marks
22/03/2024 Nearly all petroleum industry executives believe that the Norwegian Offshore Directorate is achieving its objective to contribute to the greatest possible value for the broader society from the oil and gas industry.