Start-up consent for two pipelines

06/11/2015 The Norwegian Petroleum Directorate has granted start-up consents for the Edvard Grieg oil pipeline and the Utsira High gas pipeline.

These transport solutions will become part of the development of the Edvard Grieg and Ivar Aasen fields on the Utsira High in the North Sea. Start-up of the Edvard Grieg field is planned towards the end of 2015, whereas the planned start-up of Ivar Aasen is scheduled for next year. Ivar Aasen will use both pipeline systems.

The oil transport system includes a 43-kilometre long 28-inch pipeline between the Edvard Grieg platform and a new Y-connection point, which has been installed on the Grane oil pipeline about 4 kilometres from Grane.

The gas transport system includes a 94-kilometre long 16-inch pipeline from the Edvard Grieg platform to an underwater connection point (T-connection) on the Beryl pipeline. This, in turn, is connected to the Scottish Area Gas Evacuation (SAGE) pipeline in the UK sector.

The licensees for the two transport systems are the same as for Edvard Grieg and Ivar Aasen. Statoil has been the operator of both transport systems since Plan for Installation and Operation (PIO) was approved in 2014. Gassco will take over as operator of the Utsira High gas pipeline when it comes on stream.

The two transport systems have both been delivered according to schedule. Investments for both have been lower than projected in the PIO.

Illustration

Updated: 18/12/2015

Latest news

Oil and gas discovery northeast of the Skarv field in the Norwegian Sea – 6507/3-15
12/08/2022 Aker BP ASA, operator of production licence 941, has concluded the drilling of wildcat well 6507/3-15.
NPD to present new resource report
04/08/2022 On Thursday, 25 August, Kjersti Dahle Grov, Director of Technology, Analysis and Coexistence, will present the Resource Report 2022.
Drilling permit for well 6507/8-11 S
03/08/2022 The Norwegian Petroleum Directorate (NPD) has granted Equinor Energy AS drilling permit for well 6507/8-11 S, cf. Section 13 of the Resource Management Regulations.
Dry well near the Brage field in the North Sea – 31/4-A-13 C
29/07/2022 Wintershall Dea Norge AS, operator of production licence 055, has concluded the drilling of wildcat well 31/4-A-13 C.
High level of activity on the Norwegian shelf in the first half of 2022
20/07/2022 50 years after the Storting (parliament) decided to establish the Norwegian Petroleum Directorate (NPD), there is still plenty of activity on the Norwegian shelf.
Production figures June 2022
20/07/2022 Preliminary production figures for June 2022 show an average daily production of 1 529 000 barrels of oil, NGL and condensate.
Drilling permit for well 31/1-3 S and 31/1-3 A
20/07/2022 The Norwegian Petroleum Directorate (NPD) has granted Equinor Energy AS drilling permit for well 31/1-3 S and 31/1-3 A, cf. Section 13 of the Resource Management Regulations.
Gas discovery near the Skarv field in the Norwegian Sea – 6507/2-6
13/07/2022 Aker BP ASA, operator of production licence 261, has concluded the drilling of wildcat well 6507/2-6.
Dry well near the Fenja field in the Norwegian Sea – 6306/3-2
11/07/2022 ConocoPhillips Skandinavia AS, operator of production licence 935, has concluded the drilling of wildcat well 6306/3-2.
Temporary appointment - Director general
04/07/2022 The Ministry of Petroleum and Energy has announced a temporary appointment, naming Torgeir Stordal (60) as Director General of the NPD from 30 June and until a new Director General of the NPD is hired.