Want to secure the resources on Johan Sverdrup

28/04/2015 On Friday, the Government submitted a proposition to the Storting for the Plan for Development and Operation (PDO) for the first development phase step on the Johan Sverdrup field in the North Sea.

The Norwegian Petroleum Directorate (NPD) has been in close dialogue with the licensees to ensure the resources are managed in the best possible manner.

Johan Sverdrup is the largest development on the Norwegian shelf since Oseberg, where the PDO was submitted in 1984. The total investments for the first development phase, as well as the transport systems, are estimated at NOK 117 billion.

The NPD has prepared a separate cost estimate, which is about 10 billion 2015-NOK higher than the estimate in the PDO. The most important reason for this is that production from the field will most likely be delayed by six months, according to the NPD's assessment. Though the cost estimate is higher, it is well within the uncertainty range of plus/minus 20 per cent as indicated in the development plan.

Start-up of Johan Sverdrup is scheduled for December 2019, and the field’s resources provide a basis for production for about 50 years. The expected recovery is 352 million standard cubic metres (Sm3) of oil and 13.1 billion Sm3 of gas. This yields an oil recovery rate of 63 per cent. The operator, Statoil, has shown that various measures can lead to improved recovery, and consequently, a higher recovery rate. The NPD has encouraged licensees to choose measures that will contribute to this, and the plan facilitates the use of alternating water and gas injection. Adding polymer to the injection water is another measure that could improve recovery, and the NPD has been eager to ensure the method can be used.

The large resource volume and the extensive geographical scope necessitate the drilling of many wells on Johan Sverdrup. The drilling platform will therefore have a considerable number of available well slots so that more wells can be drilled later on. Flexibility in the development solution was a key point of the NPD’s follow-up. In order to safeguard future possibilities, a decision was made for the facilities to have available weight and space capacity so more equipment can be installed along the way.

Johan Sverdrup is the sixth field on the Norwegian continental shelf that will have power from shore. Additional transmission capacity will be established by 2022 so that the fully developed Johan Sverdrup, as well as Gina Krog, Edvard Grieg and Ivar Aasen, can have the same solution.

The NPD is an advocate of cost-efficient measures that can reduce emissions to air and discharges to sea. Produced water will be cleaned and reinjected into the reservoir. Together with the power supply from shore, this will make Johan Sverdrup the field with the lowest emissions to air and discharges to sea per produced unit on the Norwegian continental shelf.

The proposition is scheduled to be submitted to the Storting before summer.

 

Illustration: Statoil

The field center on Johan Sverdrup
Illustration: Statoil

Updated: 27/11/2015

Latest news

NPD Technology Day: Programme in place
24/03/2023 Have you remembered to sign up for the NPD Technology Day in Stavanger on 7 June?
Dry well near the Visund field in the North Sea
24/03/2023 Equinor Energy AS, operator of production licence 554, has concluded the drilling of wildcat well 34/6-6 S.
Production figures February 2023
21/03/2023 Preliminary production figures for February 2023 show an average daily production of 1 994 000 barrels of oil, NGL and condensate.
Oil and gas discovery near the Fram field in the North Sea – 35/10-9
14/03/2023 Equinor Energy AS, operator of production licence 827S, has concluded the drilling of wildcat well 35/10-9 on the Heisenberg prospect.
New Diskos data type: multi-gigapixel palynology slides
13/03/2023 The Norwegian Petroleum Directorate's digitalisation project Avatara-p has produced over thirty thousand digital palynological slides from 284 released wells. This expanding dataset of 57 terabytes is now available in Diskos.
Drilling permit for well 6406/5-2 S
13/03/2023 The Norwegian Petroleum Directorate (NPD) has granted Equinor Energy AS drilling permit for well 6406/5-2 S, cf. Section 13 of the Resource Management Regulations.
Drilling permit for well 31/2-23 S and 31/2-23 A
08/03/2023 The Norwegian Petroleum Directorate (NPD) has granted Equinor Energy AS drilling permit for well 31/2-23 S and 31/2-23 A, cf. Section 13 of the Resource Management Regulations.
Five companies have applied for CO2 storage acreage
06/03/2023 The Norwegian Ministry of Petroleum and Energy (MPE) has received applications from five companies in connection with the announcement of an area in the North Sea for potential storage of CO2 on the Norwegian shelf.
Oil discovery near the Goliat field in the Barents Sea
02/03/2023 Vår Energi ASA, operator of production licence 229, has concluded the drilling of wildcat well 7122/8-1 S
Dry well near the Edvard Grieg field in the North Sea
02/03/2023 Aker BP ASA, operator of production licence 1141, has concluded the drilling of exploration well 16/1-35 S.