Developing Troll phase three

03/07/2018 Operator Equinor and partners have submitted their Plan for Development and Operation (PDO) for the third development stage of the Troll field in the North Sea.

Production on Troll is expected to continue until around 2060. Troll consists of a large gas cap with a relatively thin underlying oil zone. The field covers an area of 710 square kilometres and contains gas and oil in three slanted fault blocks. These are Troll east, Troll west gas province and Troll west oil province.

The development of Troll consists of three phases. The first was gas production from Troll east (approved in 1986 and updated in 1990). The second was oil production from the Troll west provinces (approved for the first time in 1992, followed by multiple approved additions and amendments). And the third phase – for which an amended PDO has now been submitted – comprises the gas cap in Troll west. Production is scheduled to start in the first half of 2021.

The Troll field is located about 80 kilometres west of Bergen. Water depth over the field is between 300 and 340 metres. Production start-up took place in 1995. Following approximately 23 years of production, Troll has delivered about 900 million standard cubic metres of oil equivalents (oil and gas corresponding to 5,6 billion barrels). Remaining reserves are estimated at approximately 870 million cubic metres (5,4 billion barrels).

The Troll field is a gas giant that delivered 36,7 billion standard cubic metres in 2017. At the same time, Troll has been the largest oil producer on the Norwegian shelf for several years. The oil is produced from a thin oil zone and the licensees have been at the forefront of using advanced technology for (horizontal) wells and completion. This also resulted in the licensees on Troll receiving the Norwegian Petroleum Directorate’s first IOR prize in 1998.

Image of assistant director Arvid Østhus- There are still considerable remaining oil and gas resources to recover from Troll, and the Norwegian Petroleum Directorate is therefore still concerned with the balance in the extraction of oil and gas, says Arvid Østhus (see photo), assistant director for Development and operations in the northern North Sea in the Norwegian Petroleum Directorate.

Read more about Troll’s development solutions, investments and reservoir.

Equinor’s sketch of the development solution for Troll phase three.

Equinor’s sketch of the development solution for Troll phase three.

Updated: 04/07/2018

Latest news

NPD Technology Day: Programme in place
24/03/2023 Have you remembered to sign up for the NPD Technology Day in Stavanger on 7 June?
Dry well near the Visund field in the North Sea
24/03/2023 Equinor Energy AS, operator of production licence 554, has concluded the drilling of wildcat well 34/6-6 S.
Production figures February 2023
21/03/2023 Preliminary production figures for February 2023 show an average daily production of 1 994 000 barrels of oil, NGL and condensate.
Oil and gas discovery near the Fram field in the North Sea – 35/10-9
14/03/2023 Equinor Energy AS, operator of production licence 827S, has concluded the drilling of wildcat well 35/10-9 on the Heisenberg prospect.
New Diskos data type: multi-gigapixel palynology slides
13/03/2023 The Norwegian Petroleum Directorate's digitalisation project Avatara-p has produced over thirty thousand digital palynological slides from 284 released wells. This expanding dataset of 57 terabytes is now available in Diskos.
Drilling permit for well 6406/5-2 S
13/03/2023 The Norwegian Petroleum Directorate (NPD) has granted Equinor Energy AS drilling permit for well 6406/5-2 S, cf. Section 13 of the Resource Management Regulations.
Drilling permit for well 31/2-23 S and 31/2-23 A
08/03/2023 The Norwegian Petroleum Directorate (NPD) has granted Equinor Energy AS drilling permit for well 31/2-23 S and 31/2-23 A, cf. Section 13 of the Resource Management Regulations.
Five companies have applied for CO2 storage acreage
06/03/2023 The Norwegian Ministry of Petroleum and Energy (MPE) has received applications from five companies in connection with the announcement of an area in the North Sea for potential storage of CO2 on the Norwegian shelf.
Oil discovery near the Goliat field in the Barents Sea
02/03/2023 Vår Energi ASA, operator of production licence 229, has concluded the drilling of wildcat well 7122/8-1 S
Dry well near the Edvard Grieg field in the North Sea
02/03/2023 Aker BP ASA, operator of production licence 1141, has concluded the drilling of exploration well 16/1-35 S.