Improved execution of development projects

Installasjon-av-Dvalin-modul-Heidrun-019

13/03/2020 A review of 66 projects on the Norwegian continental shelf (NCS) in 2007-18 reveals that most have kept their cost within the estimates given in their plan for development and operation (PDO).

This emerges from the report on Project execution on the Norwegian continental shelf (pdf), which the Norwegian Petroleum Directorate presented on Friday 7 February.

“The big picture shows that the projects have progressed positively in terms of both cost control and planned execution,” says Niels Erik Hald, assistant director development and operations at the NPD.

“This emphasises the importance of the companies pursuing detailed early-phase work in projects. That said, it’s also important to go on working hard to improve the execution of new developments even further.”

The report compares costs, start-up time and reserve developments with the estimates made in the PDO. Just over 80 per cent of projects have ended up with their costs within or below the uncertainty range (plus/minus 20 per cent) in the estimates.

Subsea developments very often make good progress. Ninety per cent of these have been completed in accordance with or below the PDO forecast.
Experience indicates that platform developments are more challenging, and a number of these have experienced cost overruns.

The review nevertheless shows that over 70 per cent of them end up in line with their estimated cost.

Market developments since the oil price slump have also contributed to a positive trend because the availability of resources and capacity at suppliers was better than in earlier years.

On average, completed projects have taken about 3.5 months longer than planned. The average delay is greater for platform developments than for those based on subsea installations.

The last time the NPD conducted a similar survey was in 2013, under the title Vurdering av gjennomførte prosjekter (not available in English). That covered experience with and lessons learnt from five development projects.


More reports

 

Updated: 13/03/2020

Latest news

Preparing Nova for start-up
30/06/2022 The authorities have granted consent to start production from the Nova field in the North Sea.
Drilling permit for well 25/7-10
28/06/2022 The Norwegian Petroleum Directorate (NPD) has granted ConocoPhillips Skandinavia AS drilling permit for well 25/7-10, cf. Section 13 of the Resource Management Regulations.
Drilling permit for well 6607/12-5
27/06/2022 The Norwegian Petroleum Directorate (NPD) has granted Equinor Energy AS drilling permit for well 6607/12-5, cf. Section 13 of the Resource Management Regulations.
Prestigious UN post for Harald Brekke
23/06/2022 Senior geologist Harald Brekke has been elected to the Commission on the Limits of the Continental Shelf (CLCS).
Production figures May 2022
21/06/2022 Preliminary production figures for May 2022 show an average daily production of 1 831 000 barrels of oil, NGL and condensate.
Dry well near the Kvitebjørn field in the North Sea – 34/9-1 S
21/06/2022 Equinor Energy AS, operator of production licence 1049, has concluded the drilling of wildcat well 34/9-1.
Ingrid Sølvberg resigns as Director General
17/06/2022 Sølvberg has today, Friday 17 June, resigned from her position as Director General for the Norwegian Petroleum Directorate.
Is the glass half-empty or half-full?
17/06/2022 There's no reason to sit back and rest on our laurels when an old field reaches tail production.
Minor gas discovery southwest of the Skarv field in the Norwegian Sea – 6507/4-3 S
16/06/2022 ConocoPhillips Skandinavia AS, operator of production licence 1064, has concluded the drilling of wildcat well 6507/4-3 S in the Norwegian Sea.
Dry well near the Ormen Lange field in the Norwegian Sea – 6305/5-C-3 H
15/06/2022 Equinor Energy AS, operator of production licence 209, has concluded the drilling of wildcat well 6305/5-C-3 H.