Ten more years for Troll B

Credit_-_Øyvind_Hagen_-__Statoil_-_Troll_B_platform_-_1158604

Troll B has produced more than one billion barrels of oil. Planning is now under way for another ten years of value creation. (Photo: Equinor/Øyvind Hagen)

20/04/2020 The authorities have granted consent to operator Equinor and the other licensees for a 10-year lifetime extension for the Troll B facility in the North Sea.

The extended lifetime for Troll B also includes the oil and gas pipelines that were included in the approved Plan for Development and Operation (PDO). The current consent expires in September this year. The Troll B start-up date was in September 1995.

Extension of Troll B’s lifetime to 2030 is one of the potential solutions for further developing gas production from the Troll Vest gas cap, Troll phase three.

Nine seismic surveys have been carried out on the Troll field, with the last one completed last summer.

All previous surveys have contributed to identify new well targets. The licensees expect the results from processing the data from the latest seismic survey will yield additional well targets. These can be drilled from the subsea templates tied to Troll B.

“Extended operation of Troll B secures a foundation for good resource management of significant oil and gas resources from the gigantic Troll field,” says Arvid Østhus, Assistant director Development and operations, North Sea in the NPD.

The Petroleum Safety Authority has also approved extended operation and believes that Troll B can be operated safely until the end of the licence period, based on an assessment of current technical integrity. This requires maintenance and modifications according to the lifetime extension plan.

Read more about the Troll field

 

Updated: 20/04/2020

Latest news

Correction of production figures October 2022
25/11/2022 NPD has made an adjustment to the preliminary gas-production figures for October.
Welcome to IEA Technical Collaboration workshops
10/11/2022 22. – 23. November: Research and experience on Enhanced Oil Recovery. 24. November: "Oil and gas in the context of energy security and transition".
Drilling permit for well 25/10-17 S
10/11/2022 The Norwegian Petroleum Directorate (NPD) has granted Aker BP ASA drilling permit for well 25/10-17 S, cf. Section 13 of the Resource Management Regulations.
Drilling permit for well 16/1-35 S
08/11/2022 The Norwegian Petroleum Directorate (NPD) has granted Aker BP ASA drilling permit for well 16/1-35 S, cf. Section 13 of the Resource Management Regulations.
All status reports are now on the FactPages and the FactMaps
04/11/2022 All available status reports (relinquishment reports) are now available on the FactPages.
Gas/condensate discovery near the Oseberg field in the North Sea
04/11/2022 OMV (Norge) AS, operator of production licence 1100, is in the process of concluding the drilling of exploration wells 30/5-4 S and 30/5-4 A.
Announcement: Acreage for CO2 storage on the Norwegian Continental Shelf
02/11/2022 On 2 November 2022, the Ministry of Petroleum and Energy announced an area for CO2 storage pursuant to the CO2 Storage Regulations.
Sharing data from older wells
31/10/2022 Production and injection data from older wellbores is now available in Diskos.
Impact assessment for mineral activity on the Norwegian continental shelf
27/10/2022 The impact assessment in connection with the opening process for seabed mineral activities is now being put forward for consultation, with a deadline for responses of 27 January 2023.
Drilling permit for 6407/8-8 S
27/10/2022 The Norwegian Petroleum Directorate (NPD) has granted Neptune Energy Norge AS drilling permit for wellbore 6407/8-8 S, cf. Section 13 of the Resource Management Regulations.