Oljedirektoratet

Solveig secures consent for start-up

Solveig3-satelitt

This autumn, the Solveig field will start production from subsea facilities tied into the Edvard Grieg field in the North Sea. (illustration: Lundin)

02/09/2021 The authorities have granted consent for start-up of the Solveig field in the North Sea. Operator Lundin plans to start up the field this autumn.

Solveig (PL 359 LINK) will produce from subsea production facilities tied into the Edvard Grieg field, 15 kilometres away. The oil and gas will be processed there before further transport.

Phase 1 consists of three wells for oil production, along with two wells that will be used to inject water. The field is expected to produce up to 2041.

The investment decision for Phase 2 will come later, based on experience and information from Phase 1.

The Plan for Development and Operation (PDO) estimated recoverable reserves from Solveig at 9.2 million standard cubic metres (Sm3) of oil equivalent in Phase 1. This is distributed between 6.98 million Sm3 oil (44 million bbls), 1.44 billion Sm3 sales gas and 0.42 million tonnes NGL.

The PDO estimated total investments in Phase 1 at about NOK 6.5 billion (2019-kroner).

Field: SOLVEIG - Norskpetroleum.no

Updated: 02/09/2021

Latest news

The gas bank in the Barents Sea
08/12/2023 Analyses show that the Barents Sea contains significant resources, probably more gas than oil. What needs to be done if Norway is to supply Europe with the requested volumes of gas?
Plenty of potential in tight reservoirs
06/12/2023 There are vast proven gas resources on the Norwegian shelf which are currently without development plans. Much of this gas is located in tight reservoirs – which makes it difficult to produce.
Drilling permit for well 7219/6-1
06/12/2023 The Norwegian Petroleum Directorate (NPD) has granted Vår Energi AS drilling permit for well 7219/6-1 in production licence 1025 S, cf. Section 13 of the Resource Management Regulations.
Valuable gas resources untouched
05/12/2023 The Norwegian Petroleum Directorate (NPD) has conducted a mapping of gas resources that, for various reasons, have yet to be developed. Several of these discoveries could be produced in a manner that is profitable from a socio-economic perspective.
Drilling permit for well 15/9-25
30/11/2023 The Norwegian Petroleum Directorate (NPD) has granted Harbour Energy Norge AS drilling permit for well 15/9-25 in production licence 1138, cf. Section 13 of the Resource Management Regulations.
Production figures October 2023
21/11/2023 Preliminary production figures for October 2023 show an average daily production of 1 981 000 barrels of oil, NGL and condensate.
Name change for the NPD
16/11/2023 The Norwegian Petroleum Directorate (NPD) is changing its name to the Norwegian Offshore Directorate as of 1 January 2024. The new name reflects the additional responsibilities assigned to the directorate in recent years.
Drilling permit for well 35/11-28 S
16/11/2023 The Norwegian Petroleum Directorate (NPD) has granted Equinor Energy ASA drilling permit for well 35/11-28 S in production licence 248 C, cf. Section 13 of the Resource Management Regulations.
Drilling permit for well 35/6-4 A
15/11/2023 The Norwegian Petroleum Directorate (NPD) has granted Neptune Energy Norge AS drilling permit for well 35/6-4 A in production licence 929, cf. Section 13 of the Resource Management Regulations.
First offshore wind data sets available in Diskos
13/11/2023 The Norwegian Petroleum Directorate (NPD) has collected and prepared the first data sets for offshore wind on the Norwegian shelf.